The importance of installing the FFU fan filter unit in the laboratory

The importance of installing the FFU fan filter unit in the laboratory

The installation of the laboratory FFU (fan filter unit) is an important part of the laboratory ventilation system and is of great significance for ensuring laboratory air quality and creating a safe experimental environment. This article will introduce the installation process and precautions of the laboratory FFU in detail to help you complete the installation work smoothly.
FFU selection and preparation
FFU selection: Select the appropriate FFU model according to the purpose, area, number of personnel, and other factors of the laboratory. Under normal circumstances, the air volume of the laboratory FFU is 400-600 cubic meters/hour.
Prepare tools: Prepare the tools required to install the FFU, such as screwdrivers, wrenches, spirit levels, tape measures, etc.
Installation process
Preparation before installation: Make sure that the FFU is placed on a flat and level ground, and leave enough space around it for easy installation and maintenance.
Install the frame: Install a suitable frame according to the model and size of the FFU. The frame should be fixed to the ground to ensure stability.
Install the FFU: Place the FFU in the frame and adjust the FFU position so that it fits tightly with the frame.
Connect the fan: According to the wiring diagram of the FFU, connect the power cord of the fan to the power interface of the FFU. Make sure the connection is correct and firm.
Install the filter: Open the front panel of the FFU and install the filter inside the FFU. Pay attention to the direction of the filter to ensure the correct direction of air circulation.
Sealing: Use sealing strips to seal the joints of the FFU to prevent air leakage.
Debugging: Turn on the FFU, check whether the fan is running normally, and whether the filter is blocked, and adjust the air volume to the appropriate value.
Acceptance: After the installation is completed, conduct an acceptance to ensure that the FFU is running normally and meets the laboratory air quality requirements.
Precautions
During the installation process, ensure that the FFU is placed horizontally to avoid affecting the operation of the fan.
When connecting the power cord, pay attention to the circuit voltage and ensure that the power cord matches the interface of the FFU.
When installing the filter, do not touch the surface of the filter to avoid affecting the filtering effect.
When sealing, ensure that the sealing strip fits firmly to prevent air leakage.
During the debugging process, pay attention to the operating status of the fan and deal with abnormal conditions in time.
Summary
Laboratory FFU installation is an important part of the laboratory ventilation system. Through the above introduction, I believe you have a deeper understanding of the installation process and precautions of laboratory FFU. In the actual operation process, please be sure to install it according to the specifications to ensure the laboratory air quality and create a safe and comfortable working environment for the experimenters.