How are modular cleanrooms installed?

How are modular cleanrooms installed?

I. Preparation beforehand
1. Understand in advance the modular cleanroom installation floor, cargo access, whether there is a lift transport, available lifting platform, etc., to avoid encountering the size of the goods and the size of the entrance and exit not match, to reduce unnecessary trouble, and enhance the efficiency of the assembly work.

2. Arrive at the site of the goods category classification, while the modular cleanroom installation location for the line positioning, clear the specific installation location, and determine the direction of the door, equipment, and electrical box location.

II. Installation
1. By the modular cleanroom installation order, the first wall installation, reserved door frame, and power line position; in the ceiling installation should pay attention to the body of the existing roof structure, measure the height of the top, whether there is a ceiling, or whether the need for a second hanging.

2. After the ceiling installation is completed, install the drag board, FFU fan, lamps, sockets, enclosure boards, etc., and then install the modular cleanroom supporting equipment and door panels, such as the air shower room, cargo shower room, clean doors, and windows.

3. Confirm the position of the electric box again, connect and glue the modular clean room, lay PVC flooring based on ensuring the level of the ground, or install anti-static copper strips according to customer requirements.

III. Delivery afterward
1. Debugging of equipment, on-site cleanliness testing, removal of construction waste, dust cleaning, and cleaning to ensure that the site is clean.

2. Delivery of products, on-site performance testing, the corresponding modular cleanroom training, and information delivery to avoid damage to the equipment in use, to extend the service life of the equipment